Lights, Glass, T bar, Roofing, Grading!

9/7/2018

 
We had 45 workers on site today. Lighting is on in all corridors. The T bar grid is up in all corridors and North and East classrooms. Lighting is being installed in classrooms today. Glass has arrived and is being installed.
 
All scaffolding is now up in order for us to stucco the courtyard and both office buildings. Today we are completing the insulfoam and mesh work for the roof trim and entry areas. After county approval we stucco and install frontage wall bricks .
 
Grade Tek will have majority of Arden Way excess dirt removed and site rough graded by tomorrow in order for curbs to be framed next week. We are still awaiting two manhole vaults and covers to complete the new sewer hook up. They are in transit.
 
County demands we install two new 20 foot high Arden way street lights. It is a special height. We are scrambling to find them.
 
We are shooting for pre-Thanksgiving completion.

Comments are closed.

    Categories

    All
    Campaign Update
    Construction Update
    Donor Story
    School

    RSS Feed

Contact
Sue Kneer, campaign administrator


Telephone

916-482-9666

Email

skneer@stignatiussac.org
  • HOME
  • IMPACT
    • RENDERINGS
    • LEADERSHIP
  • PROGRESS/TIMELINE
    • DONORS
  • GIVE
  • NEWS/UPDATES
  • CONTACT