Construction update 2/8/18

2/8/2018

 
All the rock for the main building floor has been put in place. Yesterday rock was placed a yellow vinyl moisture barrier. On top of that they are putting down steel rebar in a criss cross pattern. The rebar strengthens the floor and prevents cracks. Next week they will pour the entire main building with a concrete floor in 1 day. After 2 days of drying they will start framing the concrete walls.